Project context
This 20-month, 2,500 k€ program provides technical assistance for GeneXpert molecular diagnostic platforms deployed across 45 public health laboratories. The scope includes on-site technician training, critical module replacements, 24/7 remote support and a structured preventive maintenance calendar. With donor-funded budgets under close scrutiny, budget discipline and operational transparency are non-negotiable. Select a scenario below to see how the indicators evolve under different conditions.
Monitoring objectives
When a program manager reports to donors and ministry stakeholders, vague status updates are not enough. This dashboard distills complex financial data into four actionable dimensions:
- Cost and schedule performance tracking via Earned Value Management.
- Accurate Actual vs. Budget comparisons using baseline budgets.
- Forecasting of cost at completion (EAC) to anticipate funding needs.
- Clear variance analysis to support strategic reporting for senior leadership.
Performance indicators
Project completion (EV / BAC)
97.7%
Cost Performance Index (CPI)
1.01
CV: 36 k€
Schedule Performance Index (SPI)
1.00
SV: 10 k€
To Complete Performance Index (TCPI)
0.62
On track
Estimate to Complete (ETC)
57 k€
Estimate at Completion (EAC)
2463 k€
Budget at Completion (BAC): 2500 k€
Variance at Completion (VAC)
37 k€
Surplus
Performance is tracking close to the baseline plan. A CPI of 1.01 and SPI of 1.00 indicate minor variances within acceptable tolerance. No corrective action is required at this stage, but continued monitoring is recommended.
- CPI — measures cost efficiency of work performed. A value below 1 indicates cost overruns.
- SPI — measures schedule efficiency. Below 1 means the project is behind schedule.
- ETC — forecast of remaining costs based on current performance.
- EAC — projected total cost at completion, factoring in current trends.
- TCPI — the cost performance required on remaining work to meet the budget. Above 1 means the team must become more efficient.
- VAC — the projected difference between budget and final cost. Negative values indicate an expected overrun.
Financial status analysis
Financial status & remaining work
At 97.7% completion, earned value and actual costs remain broadly aligned. The EAC of 2463 k€ is close to the 2500 k€ baseline, reflecting a program that is largely on track with limited financial exposure.
Financial breakdown — BAC and EAC reference lines shown
Project performance S-curve
This curve shows the progression of planned budget (PV), earned value (EV) and actual costs (AC). The dashed red line projects AC forward based on the current scenario trend; the vertical line marks “today”.
S-curve — PV, EV, AC over time with AC projection
Key indicators overview
Variance bars — CV, SV, VAC, ETC, EAC
Cost Variance (CV) — Difference between value earned and actual cost (EV minus AC).
Schedule Variance (SV) — Difference between planned work and work done.
Estimate to Complete (ETC) — Forecast of remaining costs based on current trends.
Estimate at Completion (EAC) — Total projected project cost compared to the original budget.
To Complete Performance Index (TCPI) — Required cost efficiency on remaining work to finish within budget.
Variance at Completion (VAC) — Projected difference between budget and final cost (BAC minus EAC).
Toward real-time automation
This analysis can evolve into a fully automated dashboard by integrating with the organization’s data ecosystem.
ERP or Salesforce integration
Automatically sync budget, expenditure and activity data to eliminate manual updates and reduce human error.
Python or Power BI pipelines
Schedule scripts to run nightly, processing incoming data and refreshing visuals with zero manual intervention.
Management decision support
Publish key indicators in real time to executive dashboards used by donors, senior leadership and program managers.
Threshold alerts
Automatically notify users when the project is overspending or delayed, with suggested corrective actions.
The goal is clear: move from periodic, manual reporting to a live control room where project health is always visible and decisions are always data-driven.